Importing 1688 Goods for Tet 2027: Factory Closures, Deadlines

Short answer

Tet Dinh Mui falls on Saturday 06/02/2027 in both Vietnam and China. China's statutory Spring Festival holiday is 4 days from New Year's Eve on 05/02/2027; the State Council's adjusted 2027 holiday schedule had not been announced as of 02/11/2026. By the Tet 2026 precedent, two purchasing agents set their cut-off for delivery before Tet 23 to 28 days before Tet (each in its own way), and clearance at the Lang Son border gates on the Chinese side was disrupted from the 28th of the last lunar month to day 7. Work the order schedule back from the date the goods must be on the shelf, then confirm with each factory and forwarder.

Lunar New Year is the longest holiday of the year in both Vietnam and China, and it falls on the same day in the two countries. For sellers who import from China, that means that for about a month around Tet, factories stop dispatching, forwarders stop taking orders, clearance at the border gates is disrupted and domestic carriers pause, while demand on the platforms rises just before Tet. Goods arriving a few days late can miss the whole selling season.

This article sets out the Tet Dinh Mui 2027 dates that have been announced, those that have not, the Tet 2026 precedents for factories, forwarders, border gates and carriers, how to work back the order deadline, how to size the quantity, and customs cautions for the peak season. Sources were read on 02/11/2026. 2027 dates inferred from precedent are marked as estimates, and the figures in the examples are assumptions. This article does not replace advice from a lawyer or accountant for a specific case.

Tet Dinh Mui 2027 dates: announced and not yet announced#

Date When Status and source
Day 1 of Tet Dinh Mui Saturday 06/02/2027, the same in Vietnam and China Lunar calendar; Notice 11483/TB-BNV
Tet leave for Vietnamese civil servants 04/02/2027 (28th of the last lunar month) to 10/02/2027 (day 5), 7 days Announced, Notice 11483/TB-BNV
Tet leave for business employees One of 3 options: 1 day at the end of the Binh Ngo year and 4 days at the start of Dinh Mui, 2 and 3, or 3 and 2; at least 30 days' notice Announced, Notice 11483/TB-BNV
China's statutory Spring Festival holiday 4 days: New Year's Eve 05/02/2027 to day 3, 08/02/2027 National holiday rules as amended by State Council Order 795, applying from 01/01/2025
China's adjusted 2027 holiday schedule Not announced as of 02/11/2026 The 2026 schedule was announced on 04/11/2025 and the 2025 schedule on 12/11/2024
Spring Festival travel season (chunyun) 2027 Not announced In 2026 it ran 40 days, from 02/02/2026 to 13/03/2026 (State Council Information Office)
Border gate and forwarder schedules for Tet 2027 Not announced See the Tet 2026 precedents below

China's official holiday is usually longer than the 4 days set by law because of swapped working days. In 2026 the State Council announced a 9-day Spring Festival holiday, from 15/02/2026 (28th of the last lunar month) to 23/02/2026 (day 7), with the two Saturdays 14/02 and 28/02/2026 as make-up working days (Xinhua). The 2027 schedule may follow a similar pattern or a different one; sellers should wait for the official notice rather than guess.

When Chinese factories close for Tet#

The statutory holiday and the State Council schedule are only the frame. Each factory sets its actual schedule; the two dates that matter to a buyer are the last dispatch date before Tet and the first dispatch date after Tet, which differ between factories and have no common official statistics.

Some reference points for the length of the disruption:

  • The Spring Festival travel season. In 2026 the travel season began 15 days before Tet and ended 24 days after Tet. This is a period of heavy travel, including workers going home for Tet and returning to work.
  • 1688's shipping rule. Under 1688's shipping management rule (ruleId 20001653, revised 15/05/2026), shipping deadlines during Spring Festival and National Day follow the platform's separate notices, not the ordinary deadlines.
  • Ordinary dispatch deadlines. Under the category dispatch deadline rule (ruleId 20003583), in-stock goods are recommended to ship within 48 hours, at most 5 days depending on category; custom-made goods up to 45 days. The exact deadline depends on the category, quantity tier and the seller's commitment, so check the deadline shown on each order; a large order may fall into the custom-made tier even if the product is listed as in stock.

A question to send to each supplier before confirming a Tet order, written in Chinese to avoid misunderstanding:

您好,请问贵司2027年春节放假和开工的具体日期?春节前最后发货日期是哪天?如果现在下单这个数量,最晚哪天能发货?

Meaning: "On what dates does your factory close and reopen for Spring Festival 2027? What is the last dispatch date before the festival? If I order this quantity now, what is the latest date you can ship?". Keep the message confirming the dispatch date to compare against or to provide if a complaint is needed; under rule 20001653, separate agreements and the seller's commitments are considered before the platform's default, but the platform decides how to handle each case.

Forwarders, border gates and domestic carriers at Tet, by precedent#

As of 02/11/2026 none of the parties below had announced a Tet 2027 schedule. The table summarises Tet 2026 schedules (day 1 of Tet was 17/02/2026) that were published, so sellers can see the order and spacing of the dates.

Party Dates before Tet 2026 Closure and reopening Source
Viet Trung Company (consignment, purchasing agent) Stopped taking Taobao, 1688 and Pinduoduo purchasing-agent orders from 20/01/2026 (28 days before Tet); Guangzhou warehouse worked until 31/01/2026, Pingxiang warehouse until 01/02/2026 Warehouses and offices reopened 26/02/2026 (day 10) Viet Trung Company notice
1688online (purchasing agent) New orders for delivery before Tet accepted until the end of 25/01/2026 (23 days before Tet); later orders still accepted but delivered after Tet Closed from 14/02/2026 to the end of 23/02/2026 1688online notice
Lang Son border gates, Chinese side Clearance paused from 15/02/2026 (28th of the last lunar month) Huu Nghi, Tan Thanh and Coc Nam stopped 15/02 to 18/02, then only pre-registered goods 19/02 to 23/02; Chi Ma only pre-registered goods 15/02 to 23/02; Na Hinh stopped 15/02 to 23/02; normal from 24/02/2026 (day 8) Dong Dang Border Gate Economic Zone Management Board, Lang Son, via Tax and Customs Review
GHN (domestic delivery) Recommended creating orders before 08/02/2026; per-route guidance for delivery before Tet ran from before 09/02/2026 (inter-province, inter-region) to before 13/02/2026 (intra-province Ho Chi Minh City, Hanoi) Nationwide pause 16/02 to 19/02, back 20/02/2026 (day 4); COD reconciliation closed 14/02 to 22/02 GHN notice

The table includes only parties with a public notice on their website at the date read; being named is not an assessment of service quality. For orders using shipping services supported by TikTok Shop or Shopee, sellers should follow the operating schedule and handover deadlines the platform publishes close to Tet; for orders where the seller arranges shipping, also check the schedule of the carrier in use and still meet the platform's order handling deadlines. On Shopee, the order handling deadline of the Express channel can change over holidays and Tet, per a Shopee Seller Education page.

The precedents show three things. The purchasing-agent cut-offs of the two parties (one stopped taking orders, the other took only new orders for delivery before Tet) came earliest, about 3 to 4 weeks before Tet, far earlier than the point when clearance was disrupted; these are purchasing-agent service dates, not the last date a China warehouse accepts consigned goods, and the two should be asked about separately with each party. Reopening after Tet is not simultaneous: the border gates were back to normal from day 8, one forwarder's warehouse from day 10, and the first batch to reach a Vietnam warehouse depends on when factories resume dispatch and the actual processing time after reopening. Domestic carriers stop last, but the deadline for taking orders for delivery before Tet for each shop also depends on the platform's order handling schedule, the delivery route and packing time.

Estimating Tet 2027 dates from the 2026 precedents#

If the 2027 dates keep the same spacing from day 1 of Tet as in 2026, the equivalent dates are as in the table below. These are estimates for rough planning, not published schedules; each party may set a different timetable.

Tet 2026 precedent Before day 1 of Tet Equivalent Tet 2027 date (estimate)
Viet Trung Company begins to stop taking purchasing-agent orders 28 days before 09/01/2027
1688online takes new orders for delivery before Tet until the end of 23 days before 14/01/2027
Viet Trung Company's Pingxiang warehouse works until the end of 16 days before 21/01/2027
GHN recommends creating orders before 9 days before 28/01/2027
Lang Son border gates, Chinese side, pause 2 days before 04/02/2027
Lang Son border gates back to normal Day 8 13/02/2027
Viet Trung Company warehouses reopen Day 10 15/02/2027

When the parties publish official schedules, sellers should replace the estimated dates with the real ones and rebuild the order calendar.

Working back the order schedule from the shelf date#

A purchasing agent's cut-off answers the question "what is the latest I can order to have the goods arrive before Tet" for that purchasing-agent service. A Tet seller's question is different: when must the goods be in the warehouse and listed to catch the whole selling season. The order schedule should therefore be worked back from the start of selling, stage by stage:

Stage Time basis Note
Inspection, photos, listing The shop's own capacity Counting, sampling and a written report on receipt
From the forwarder's China warehouse to the Vietnam warehouse Ma Toc's public price list (read 02/11/2026) shows Guangzhou or Pingxiang to Hanoi in 2 to 4 days and to Ho Chi Minh City in 6 to 8 days (consignment price list) One carrier's published time, for normal periods; add a buffer in peak season
From factory to forwarder warehouse Depends on the domestic courier and the distance How to read the time of each stage is in the article on how long importing from 1688 to Vietnam takes
Factory dispatch In-stock goods up to 5 days, custom-made goods up to 45 days under 1688's rules Use the seller's commitment for the right quantity tier

Hypothetical example for a Tet decoration product#

A seller of Tet decorations imports in-stock goods from 1688, shipped by road consignment to a Hanoi warehouse. All figures below are assumptions for illustration:

  • The seller wants the goods on the shelf from 15/12/2026, for about 7 weeks of selling before Tet.
  • Inspection and listing take 3 days: goods must be in the Hanoi warehouse by 12/12/2026 at the latest.
  • Shipping from the forwarder's warehouse to Hanoi takes 8 days, double the upper end of the published time, as a peak-season buffer: goods must reach the forwarder's warehouse in China by 04/12/2026 at the latest.
  • Domestic shipping in China from factory to forwarder takes 3 days: the factory must dispatch by 01/12/2026 at the latest.
  • The factory commits to dispatch within 5 days: the order must be placed and paid by 26/11/2026 at the latest.

For a top-up batch, the seller needs to ask about three dates separately: the last date for purchasing-agent orders (if using a purchasing-agent service), the last date the China warehouse accepts consigned goods, and the expected date the shipment reaches Vietnam. These dates can differ by party and service, and one should not be used to infer another. By the precedents, the cut-off for purchasing-agent orders for delivery before Tet could fall around 09/01/2027 to 14/01/2027 (estimate), so there may be only one top-up opportunity before Tet. The seller should decide the top-up from the end of December, based on the selling rate of the first two weeks.

Which shipping method is faster and cheaper for each type of goods is covered in the article on shipping 1688 goods to Vietnam.

Customs clearance in the Tet peak#

Goods imported from China by road are directly affected by the border gate schedule. The Tet 2026 precedent shows that clearance on the Chinese side was disrupted from the 28th of the last lunar month to day 7, with some gates stopping entirely and some handling only pre-registered goods. The 2027 schedule will be announced close to Tet by the Dong Dang Border Gate Economic Zone Management Board in Lang Son and the equivalent bodies in other provinces.

Points to prepare by way of importing:

  • Formal import under your own name on the declaration. Prepare the commercial file early and identify which documents must be submitted at customs for each shipment: declaration, commercial invoice, transport documents, and licences or specialised certificates where they apply. A certificate of origin to claim special preferential import duty can be submitted later under the conditions of the law; distinguish documents that must be submitted at clearance from documents kept for checking. Agree early with a customs broker or the forwarder which documents each party will prepare.
  • Goods subject to specialised inspection. Goods subject to quality inspection or conformity certification, such as children's toys or some electrical goods, need extra time for registration, sampling and certification. For Tet goods in this group, put inspection time into the schedule from the start.
  • Consignment or purchasing agent. Sellers need to establish whether the service provider carries out the import procedures, whose name is on the declaration and which party provides the import documents. A published order cut-off does not mean every shipment will arrive before Tet; clearance time still depends on the goods, the file and conditions at the gate.

When the clearance pause is near, a truck that has reached the gate but not completed formalities may have to wait until the gate reopens. Tet shipments should therefore be planned to cross the border some margin ahead of the pause, not right up against it.

Which month is cheaper for importing from China#

No public source shows that goods on 1688 are cheaper in any fixed month of the year. Sellers set prices themselves, usually by quantity tier, and each tier can carry a different dispatch deadline. The costs that change with timing lie elsewhere:

Item What it changes with How to handle it
CNY/VND exchange rate Changes daily with the market Calculate landed cost at the rate actually paid for each payment; see the article on the yuan exchange rate when importing from 1688
Consignment shipping rates Each carrier's price list, which may be updated Read the current price list and compare actual and volumetric weight, as in the article on charging by weight or by volume
Schedule around Tet Pre-Tet order cut-offs and post-Tet reopening dates Order Tet goods before the cut-offs; avoid piling in orders right after reopening
Goods price Quantity tiers and negotiation with the seller Combine orders to reach a tier, ask for quotes with a validity period

For Tet goods, the risk of arriving late usually outweighs any price difference that waiting might bring: a batch that arrives after Tet may have to sit in storage until next season or be sold at a discount. Choose the Tet order date by the holiday and selling calendar first, then by price. For year-round goods, imports can be scheduled to avoid two disruption windows: about a month around Tet and the weeks right before major sales; how to schedule is in the article on the import schedule before major sale events.

How much to import for Tet#

Quantity is worked out differently for two groups of products.

Goods sold only at Tet, such as decorations, red envelopes and Tet gift boxes. What is left after Tet is almost unsellable until next season. The safe approach is to split into a first batch and a top-up: the first batch on a cautious forecast, the top-up decided by the actual selling rate and ahead of the purchasing-agent and consignment cut-offs confirmed with the relevant service provider.

Year-round goods that rise at Tet, such as household goods and accessories. This group needs enough stock to sell from the last pre-Tet batch arriving until the first post-Tet batch arrives:

Quantity needed = Daily selling rate × Days still sellable in the gap + Safety stock

Hypothetical example: the last pre-Tet batch reaches the warehouse on 20/01/2027 and the first post-Tet batch on 25/02/2027. The two dates are 36 days apart. Assume the shop stops taking orders for 7 days around Tet, leaving 29 days of selling. With a selling rate of 20 units a day and safety stock of 150 units, the quantity needed when the last batch arrives is 20 × 29 + 150 = 730 units, including the remaining stock. Use the selling rate from the same period last year if available, since the month before Tet usually differs from the average.

Leftover Tet goods: clear before Tet or hold until next year#

The decision to clear Tet goods should be made before Tet, while customers are still buying. Demand for decorations and Tet gifts can fall sharply after the pre-Tet shopping peak, and goods held back tie up capital and warehouse space until next season, with the risk of outdated designs.

Legally, under clause 2 of Article 4 and point b of clause 5 of Article 3 of Circular 39/2025/TT-BCT (effective 01/07/2025), the promotion period of the 30 days immediately before Lunar New Year allows discounts of up to 100%, in place of the usual 50% cap. For Tet Dinh Mui, that period is 07/01/2027 to 05/02/2027. This cap does not replace the other requirements of promotion law, most recently amended by Decree 239/2026/ND-CP (effective 26/06/2026). A higher legal cap does not lower the economic floor price; how to calculate a discount that avoids a loss is covered in the article on TikTok Shop and Shopee flash sales.

For goods that cannot be cleared in time, how to compare the total loss from clearing against the cost of holding the stock another year is covered in the article on slow-moving stock.

Cash flow at Tet#

Tet goods send capital out earlier and bring it back later than usual:

  • Money goes out from November and December. Goods, shipping and service fees are paid on ordering and on arrival, many weeks before the selling season. Agree deposit and payment terms with the factory in writing before ordering.
  • Platform proceeds run from successful delivery. Under the TikTok Shop settlement page (page dated 09/07/2026), the payment cycle is 1, 3, 8 or 15 days from delivery, and can extend to 30 calendar days when there are signs of anomaly or risk. Under Article 10.3 of the Shopee Terms of Service, if the buyer neither confirms receipt nor requests a return, funds are credited to the Balance on day 4 after successful delivery at the earliest; if the buyer confirms, funds may be credited sooner, except where checks are needed. Shopee transfers withdrawals to the bank only on working days, and the bank may need extra time. Carriers closed for Tet slow deliveries, and the time proceeds are received slows with them.
  • COD reconciliation for self-delivered orders. For orders delivered outside the platform, carriers also pause reconciliation over Tet; in 2026 GHN did not transfer COD from 14/02 to 22/02/2026.

Build the cash plan by week from November to after Tet, including the amount needed for the first batch after Tet; how to build it is covered in the articles on the cash flow plan for importing and on profit but still short of cash.

Tet 2027 dates to watch#

Date Event Status
Early 11/2026 (by precedent) China's State Council announces the 2027 holiday schedule Not announced as of 02/11/2026
01/12/2026 to 05/01/2027 Second national concentrated promotion programme of 2026, discounts up to 100% Announced, Decision 2210/QD-BCT of 10/09/2026
12/2026 to 01/2027 Forwarders and purchasing agents announce order cut-offs and holiday schedules Not announced; Tet 2026 precedent was 28 days (stop taking purchasing-agent orders) and 23 days (new orders for delivery before Tet) before Tet
07/01/2027 to 05/02/2027 Lunar New Year promotion period, discounts up to 100% Under Circular 39/2025/TT-BCT
Close to Tet Platforms and carriers announce holiday schedules and handover deadlines Not announced
Close to Tet Tet clearance schedule of the Lang Son border gates Not announced; precedent of clearance disrupted from the 28th of the last lunar month
04/02/2027 to 10/02/2027 Tet leave for Vietnamese civil servants Announced, Notice 11483/TB-BNV
05/02/2027 to 08/02/2027 China's statutory Tet holiday; day 1 of Tet is 06/02/2027 By law; adjusted schedule not announced

Checklist for importing Tet goods#

  1. You have fixed the date goods must be on the shelf for each Tet product group and worked back to the latest order date.
  2. You have asked each supplier for the last dispatch date before Tet and the date work resumes, and kept the reply as a message on 1688.
  3. You have checked whether the order's quantity tier falls into the custom-made mode with a longer dispatch deadline.
  4. You have asked the forwarder about three dates separately: the purchasing-agent order cut-off, the last date the China warehouse accepts consigned goods, and the date the warehouse reopens; replace estimated dates with real ones.
  5. You have added a peak-season buffer to shipping time, not normal-period time.
  6. For formal imports, you have identified the documents to be submitted at clearance and the specialised inspection procedures before goods reach the border gate.
  7. Goods sold only at Tet are split into a first batch and a top-up, the top-up decided ahead of the dates confirmed with the forwarder.
  8. Year-round goods have enough stock for the gap between the last pre-Tet batch and the first post-Tet batch.
  9. You have scheduled clearance of leftover Tet goods before Tet, within the discount cap and above the floor price you calculated.
  10. You have built a weekly cash plan through to after Tet, allowing for the time platforms and carriers are closed.

Frequently asked questions

What date is Lunar New Year in 2027?
Day 1 of Tet Dinh Mui is Saturday 06/02/2027, the same day in Vietnam and China. Under Notice 11483/TB-BNV of the Ministry of Home Affairs, civil servants are off from 04/02/2027 to 10/02/2027. Businesses choose one of three leave options and must tell employees at least 30 days ahead.
When do Chinese factories close for Spring Festival?
Chinese law sets a 4-day Spring Festival holiday, from New Year's Eve to day 3; in 2026 the official holiday ran 9 days through swapped working days. Each factory sets its actual schedule, so ask each supplier for the last dispatch date before Tet and the date work resumes, and keep the reply in writing.
What is the latest date to order from 1688 for Tet 2027 sales?
As of 02/11/2026 no forwarder had announced a Tet 2027 schedule. By the Tet 2026 precedent, Viet Trung Company stopped taking purchasing-agent orders 28 days before Tet, while 1688online took new orders for delivery before Tet until the end of 23 days before Tet (later orders were still accepted but delivered after Tet); repeated, the equivalent dates would be about 09/01/2027 and 14/01/2027. These are published purchasing-agent cut-offs for delivery before Tet, not a final deadline for every way of importing, and not a deadline for making it in time to sell; Tet goods must be ordered earlier, worked back from the start of selling.
Is customs clearance of goods from China halted over Tet?
It can be disrupted, but not every border gate stops in the same way. At Tet 2026 the Chinese side paused clearance at the Lang Son gates from 15/02/2026 (the 28th of the last lunar month): Huu Nghi, Tan Thanh and Coc Nam stopped until 18/02, then handled only pre-registered goods until 23/02, Chi Ma handled only pre-registered goods, and Na Hinh stopped; operations were normal from 24/02/2026 (day 8). The Tet 2027 schedule is not yet confirmed, so follow the notices of the gate you expect to use.
Which month is cheapest for importing from China?
No public source shows that goods on 1688 are cheaper in any fixed month. Sellers set prices by quantity tier; what changes with timing is the exchange rate, the forwarder's rate card and the schedule around Tet. For Tet goods, the risk of late arrival outweighs any price difference there may be, so choose the order date by the holiday calendar.